== Outage schedule ==
Jobs will not be scheduled with a run time (<code>--time=</code>) that extends into the beginning of a planned outage period. This is so the job will not be terminated prematurely when the system goes down.
 
* '''Oct 30 Siku''': On the morning of Wednesday, October 30th there will be a brief power-outage affecting several buildings on the South Campus, including the data center that houses Siku. A Slurm reservation has been created to begin at '''6:00 am Nfld''' on Wednesday morning and prevent jobs from starting unless they will finish by that time. We expect to Siku back in service later that morning.
* '''Oct 28-30 Argo''' will be offline for electrical power work, some upgrades of infrastructure machines, and some software and firmware updates. We anticipate return to service on Thursday October 31.